Contract
Notes
A
contract states who takes a risk in a
contract, what is to be done, who is to
do it, where it takes place, when it has
to be completed and the financial
implications of all actions associated
with it.
The
tender price is no more than a record of
the value of the work at a particular
point in time based on the information
available at the
time.
There are several
factors that impact on tenders and they
are handled in different ways depending
on the size and nature of the
works
Work is often tendered
before all the documents are
complete.
The
specification may be complete but quite
often the drawings may only have reached
a 60% complete status – possibly enough
to obtain a building consent but often
with critical information or decisions
yet to be confirmed.
Designers in
this situation make allowances in the
documents to cover these costs such as
provisional sums and contingency funds.
These sums are credited from the tender
sum when the true cost is agreed at a
later
date.
Subcontractors and
suppliers to the main contractor time
‘tag’ their pricing for acceptance
commonly their price is fixed for 30
days.
Consequently
after 30 days if their price has not been
accepted they have the option of
withdrawing their
price.
If tenders have been
called prior to the obtaining of a
consent the local authority will often
have additional work required before they
will issue a consent.
As this work
was not shown on the contract documents
the contractor cannot be expected to have
been able to allow for it and
consequently will request a variation for
an increased scope of
work.
Once work has commenced
unknown site conditions such as
underground obstructions, rock, unstable
ground unmarked services or unseen
defects in the existing structure may
require instruction to the contractor
from the design
team.
Specialist imported
items may be subject to exchange rate
fluctuations and locally supplied
products will be subject to
inflation
The
client may increase or decrease the scope
of the contractors
work.
All
of the above are financial risks to the
parties to the contract and unless
documented otherwise, will constitute a
variation to the contractor’s original
tender sum as the conditions that they
priced the work under have
changed.
The
approach is generally that the risk
should be allowed for by the party
best
placed to control
it.
Time risk on tender
acceptances is the client’s risk and is
negotiated at the time of
tender.
It is
critical that the time the contractors is
able to commence work is clearly
established as delays will affects their
ability to control
costs
Changes to drawings or
increased details will not be deemed as
variations to the contractor unless they
can prove that the detail has materially
affected their scope of work, that is the
detail increase the volume of work, the
quality of finish or the time required to
carry out the work.
Otherwise it
will be deemed that the contractor had
the experience to carry out the work as
drawn.
That is, how
else was the contractor going to do the
work and how has the increased detail
changed that
process.
If
a Schedule of Quantities has been
provided then this becomes obvious with a
remeasure of the works with supporting
evidence from the
contractor.
If the change is due to
the local authority then it is always a
client risk unless there is a specific
agreement in a design and build type
contract in which case if the designer
has failed to comply with known statutory
requirements then the risk is the
designer builder.
If the
requirements have changed then the risk
may be the
clients.
With respect to time for
acceptance tags the risk is that
suppliers and subcontractors will
increase their price after the contract
has been negotiated which is a serious
risk to the contractor.
The contract
start and finish and tender acceptance
dates are critical, fixed prices from
suppliers and subcontractors must be
agreed prior to commencement and likely
dates of any price increases for supply
should be stated. Builders often tag
their prices to supplier’s price lists
and this becomes a client
risk.
In most cases the
simplest solution in small contracts is
to have the builder take the risk for the
duration of the
contract.
There is
however a point that needs to be noted
when a variation is priced as a change of
scope the builder can charge at the new
rate of supply, they should not be forced
to carry out work outside their original
scope for what might be a loss. The same
principle applies to work carried out
outside the original contract period
where the contractor has been granted an
extension of
time.
Extensions of time will
be granted to the contractor where
circumstances are beyond their
control.
Traditionally
contractors were allowed time extensions
for inclement weather, in most modern
contracts they are deemed to have allowed
for inclement weather with their tender
and no time extension is given unless the
time lost can be proven as genuine and
beyond what might reasonably have been
allowed for.
Easy
solution is for the contractor to state
days allowed for and to be granted
additional days if
proven.
Regardless
it is not normal for weather related
extensions of time to have monetary
values attached to
them.
That is the
contractor receives additional time to
carry out the work without penalty but no
cash.
This is not the case
with other extensions of time where the
contractor has been delayed by
circumstances beyond their control such
as design related issues, client supply
items, changes in scope of works
etc.
The
contractor is entitled for compensation
for the cost of continuing to run the
contract.
The cost of
running the contract for an extension of
time becomes a variation charge to the
contract.
It is critical for both
parties that the contractor’s margin for
pricing variations is agreed at the time
the contract is signed.
The margin
will include profit at a nominated rate
plus the preliminary and general charges
(on site overhead) for running the
contract.
The
contractor may add a charge for
processing variations and recovery of off
site overheads.
This can be
contentious and should be negotiated
before the works commence.
It is our
view that the contractor is entitled to
recover the cost of off site processing
of the variation plus off site
supervision where addition time is
required.
When variations decrease
the value of the contract the decrease is
exclusive of the contractor’s margin and
the cost of processing is deducted from
the decrease.
Essentially the works
are complete when the owner takes
possession.
This can be
highly contentious but in effect when the
client has use of the property it is
practically complete.
If it is not
practically complete the client should
not be given
possession.
This can be very
difficult if not clearly defined
especially when the works are within an
occupied building and the client is
employing others to fit soft furnishings,
plant and equipment
etc.
In all cases
the designer, client’s representative or
engineer to the contract should sign a
Practical Completion Certificate for the
works to be used by the client prior to
possession taking
place.
This may
apply to a section of the works and not
the entire contract – normally referred
to as sectional
completion.
The problem comes if a
Code Compliance Certificate is not
issued by the local authority
which could mean that while the building
is practically complete and the client
has been able to fit out the works they
are not able to
occupy.
Every case
is different and the clauses associated
with Practical Completion clearly
defined.
If the contractor does
not complete on time the cost to the
client should be clearly
stated.
The
liquidated damages need to be stated at
the time of tender and need to
be
justifiable.
In a
domestic situation this may be the rental
cost of temporary accommodation, the
situation for a commercial customer may
however be far more serious in that the
profitability of the client may be
affected.
On green fields sites
insurance is always the contractor’s
cost.
Where the
client is resident in an existing
structure the client should extend their
policy to include the building
works.
|